Construction updates

Information for October & November 2017

In September we filled the new water main with water and tested its operation. This was a major milestone for the project and provides confidence that the pipeline will be commissioned and ready to supply drinking water by mid-October.

Over the next two months we will be reinstating the parkland west of GE Robinson Park and the intersection of Robinson Road and Crawley Street. We will continue our work at Reservoirs 2 and 3 and decommission the existing M40 water main.

Thanks for your patience as we continue to complete this essential work.